It has been a week of milestones with the plastering of the interior coming to a conclusion. The last walls in the kitchen/dining area are being completed today so we should be fully skim plastered by the end of January as planned.
Yesterday, in the gales & hail the top run of scaffolding was removed by Nigel of Assured Access Scaffolding. The parapet capping on the main roof is complete and all the smaller roof areas are also finished. The bottom run of scaffolding will wait another few weeks until the final coat of mineral plaster finish is applied to the exterior of the ground floor, hopefully completed before the month of February is complete.
We’ll give the house a week or so to dry-out before the next stage begins with the painting of the undercoat, floor polishing of the concrete and the second fix electrics & plumbing.