Thursday 22nd November and the installation of the Heat Recovery Ventilation System has commenced.
Windy City Comfort from Monaghan are the installation company for the MHRV system.
All the pipework for the ducting , connectors and the 2 units were delivered first thing on the 22nd and the slow process of mapping out the layout began.
There were a few hurdles to overcome with a couple of points in the layout drawings not working out on site. Beams and bracing in the wrong places but Aidan McCarra was able to find solutions and soon enough the pipework was taking shape.
It’s going to take about 4 days to complete and then we wait until the house is finished and plasterboarded etc. before the system is commissioned and tested.