As we enter the 3rd week of January the plasterboarding is close to completion. Brian OSullivan & the lads have done an excellent job in fixing the plasterboard throughout the house.
All the rooms apart from the downstairs bathroom are now boarded and it is the window & door openings that need to be finished. There are also a few small areas which were left open to check for leaks, fit showers etc which have to be finished also.
Hopefully the plastering will start next week and we’ll be skim coated before the end of the month and ready to start the final fixes, plumbing and flooring.