Initial design of the gate was mocked up to work out the size, opening, wall heights etc.
The construction process involved design and build of the rolling gate frame and track frame by a local metal working firm. The motor, remote control and all comms were fitted by Active Technology a local company who were very good to deal with.
With the gate operational we had the boundary walls built by a skilled blocklayer who did some other work on the house for us. He finished the job in a couple of days but due to the arrival of winter weather we deferred the plastering until 2017.
With the arrival of spring weather we had the walls plastered and painted